Information for Grantees
MANAGING A GRANT
This webpage should give you all of the information you need on order to manage your grant. Please do not hesitate to contact National NAGPRA, with any questions you may have. Phone : (202)354-2201; Email: Nagpra_Grants@nps.gov
All NAGPRA grantees are required to comply with the terms and conditions set forth in their Grant Agreement. Please see the chart to determine when and which forms you are required to submit as part of your grant. Make certain to submit all of your reporting information on or before the due dates or your grant will become noncompliant. If your organization becomes noncompliant, further requests for an advance or reimbursement will be denied until you have regained compliance status.
Please note that 15% of your grant funds will be held until all paperwork including the final report is received and approved.
CHART OF REQUIRED FORMS
|
Form |
When to Submit |
Original Required |
Letterhead Required |
Accepted methods of Receipt |
Interim Report |
Every 6 months from start of grant Refer to your grant agreement. |
|
|
Scanned and submitted via email, fax, or mail
*FeEx preferred
|
Final Report |
90 days from completion of grant. Refer to grant agreement. |
X
|
|
Mail only *FeEx preferred |
SF-425
Federal Financial Report |
Every 6 months with interim report
With final report
30 days after receiving an advance |
|
|
Fax, mail, email unless otherwise requested |
SF-270
Request for Advance or Reimbursement |
As grantee requires funds
With final report |
Final request only |
|
Fax, mail, email unless otherwise requested |
Budget Modification |
At least 30 days prior to start of modification |
|
X |
Fax, mail, email unless otherwise requested |
Grant Extension |
At least 30 days prior to grant end date |
|
X |
Fax, mail, email unless otherwise requested |
Change in Scope of Work |
At least 30 days prior to start of work |
|
X |
Fax, mail, email unless otherwise requested |
Change in Personnel |
Immediately upon change in personnel status |
|
|
Fax, mail or email |
Competitive Negotiations Form |
Upon selection of consultants |
|
|
Scanned and submitted via email, fax, or mail |
INTERIM REPORTS
All grantees are required to submit interim progress reports. Refer to your Grant Agreement for the due date. NAGPRA grantees are required to submit an interim report every six months for the duration of the grant.
Interim Progress Report MS Word
*Note that an SF425 Federal Financial Report (FFR) is due every six months for the duration of the grant as well.
FINAL REPORTS
All grantees must submit a final report within 90 days after the end of their project or no later than the date provided in their Grant Agreement or grant extension. Grantees must include one copy of the deliverables listed in their Grant Agreement unless stipulated otherwise. Upon approval, the remaining 15% of the grant amount will be released to the grantee.
Consultation/Documentation Grants Final Report (MS Word)
Repatriation Grants Final Report (MS Word)
Final Budget Template PDF or MS Word
Required for Repatriation Grants ONLY:
Template for submitting transfer of control documentation MS Word
The following chart provides the Interim and Final Report due dates for the Consultation/Documentation grants for FY2009, FY2010 and FY2011. These dates are based on the majority of Grant Agreements issued that year. You must check your Grant Agreement for your Start and End dates and adjust reporting dates accordingly.
Consultation/Documentation Grant
Interim and Final Report Due Dates |
FY2009 Report Due Dates |
FY2010 Report Due Dates |
FY2011 Report Due Dates |
Start of Grant Period |
July 1, 2009 |
Start of Grant Period |
June 1, 2010 |
Start of Grant Period |
July 1, 2011 |
1st report |
January 31, 2010 |
1st report |
December 31, 2010 |
1st report |
January 31, 2012 |
2nd report |
July 31, 2010 |
2nd report |
June 30, 2011 |
2nd report |
July 31, 2012 |
3rd report |
January 31, 2011 |
3rd report |
December 31, 2011 |
3rd report |
January 31, 2013 |
End of Grant Period or 4th report |
July 31, 2011 |
End of Grant Period or 4th report |
June 30, 2012 |
End of Grant Period or 4th report |
July 31, 2013 |
Final Report |
October 31, 2011 |
Final Report |
September 30,2012 |
Final Report |
October 31, 2013 |
5th report* |
January 31, 2012 |
5th report* |
December 31, 2012 |
5th report* |
January 31, 2013 |
6th report* |
July 31, 2012 |
6th report* |
June 30, 2013 |
6th report* |
July 31, 2013 |
Final reports are due by the date provided above or within 90 days after completion of the project work.
* If you request an extension, you must continue to submit interim reports on a semi-annual basis, until a Final Report is submitted.
FINANCIAL REPORTS
SF425 Federal Financial Report (FFR)
The Office of Management and Budget (OMB) developed the Federal Financial Report (FFR), Standard Form (SF) 425 for use throughout the Federal Government. The FFR was designed to replace the Financial Status Report (SF269) and the Federal Cash Transactions Report (SF272) with one comprehensive financial reporting form.
The National NAGPRA Program now requires all grantees to submit the SF-425 with each interim and final report, in lieu of the SF269A and the SF272.
This form is due for three different reasons:
- Due every six months for the duration of the grant; and
- Due one month after a cash advance has been received; and
- Due with the final report
SF425 Form (PDF)
SF425 Sample (PDF)
SF270 Request for Advance or Reimbursement
Can be submitted at grantees’ discretion once they receive a Smartlink Account and password.
SF270 PDF
Expenditure Example
AUTOMATED STANDARD APPLICATION FOR PAYMENTS (ASAP)
The National Park Service has moved to a new business and accounting system called the Financial and Business Management System (FBMS). FBMS uses a payment system called the Automated Standard Application for Payments (ASAP). All current NPS grantees should have received an email containing forms to register with ASAP. If you are an existing NPS grantee and did not receive prior ASAP registration instructions, please send this form to ASAP_Enrollment@nps.gov.
ASAP will notify you via email when you are able to access the new system. The ASAP website has tutorials on the new system and answers to FAQs,http://www.fms.treas.gov/asap/index.html.
It is important to understand that the new system does not affect the terms and conditions of your grant agreement. The grant agreement, which is signed by the NPS and the Grantee, is a binding legal document, and grantees must continue to comply with all grant terms and conditions.
The SF 270 Request for Advance or Reimbursement form is no longer required to draw funds. However, if the form assists you in maintaining accurate financial records you may continue to complete it and send copies to the NPS.
To access your grant funds simply follow the instructions provided to you by ASAP. Note: If you have outstanding reports or late submittals, this may prevent you from drawing down funds.
MODIFYING YOUR GRANT
In accordance with the Grant Agreement, grantees are required to notify the National NAGPRA Program of any budgetary or programmatic changes to the original grant agreement. Most grant modifications fall into the following categories:
• Change in Personnel
• Change in Scope of Work
• Grant Extension
• Budget Modification
All grant modifications must be submitted to the National NAGPRA Program in writing. Requests for a modification will be approved in writing within 30 days of receipt as long as the grantee is in good standing. you must receive an official letter from the National Park Service stating that your request for a modification has been approved. The letter will provide either the revised budget, scope of work or end date. Grantees are responsible for reporting on all changes in their interim and final reports. The National Park Service does not send an official acknowledgement of personnel changes; however, failure to notify the National Park Service of any changes may result in delays in processing your application or disbursing funds.
Contact Sherry Hut at sherry_hutt@nps.gov, 202-354-1479; or Vedet Coleman, Grants Management Specialist at (202)354-2077 or email NAGPRA_Grants@nps.gov if you have any questions or to check on the status of your request.
PLEASE NOTE : No disbursements, modifications or extensions will be approved unless the grant is in good standing and all progress reporting is up-to-date.
You may use the information provided below to submit your request or print off the Modification Request Guide which will guide you through the information needed to request a budget modification, change in scope of work, a grant extension or a change in personnel.
Grantees must include the following information in your request for a modification:
1. Date of Request
2. Contact Information
- Grant number
- Name of grantee
- Name of contact person, mailing address, email, phone and fax
- Signature of authorized representative (can be Project director)
3. Type of Modification Request (budget, grant extension, etc.)
4. Reason for Modification Request
Provide a detailed explanation for requesting a modification. In addition, include the following information, if applicable:
- Change in Personnel – provide current employee’s name, title and contact information
- Change in Scope of Work - list the current scope of work as stated in your grant agreement
- Grant Extension – provide current end date
- Budget Modification – see Budget Modification template below
5. Revision
Provide a detailed explanation of the modification you are requesting. If applicable, include the following:
- Change in Personnel: Provide new employee’s name, title and contact information and old employee’s name, title and contact information\
- Change in Scope of Work: Provide the revised scope of work and list any new deliverables. You will be expected to provide a copy of the revised deliverables in your final report.
- Grant Extension: Provide revised End Date. Please note that grant extensions will only be given for a maximum of one year after the current end date. Additional extensions may be granted depending on the circumstances involved. Grant extensions must be requested in writing before the grant expires
Budget Modification: Use template provided below.
Budget Modification Template Line Item |
Original Budget (use budget in grant agreement or prior budget modification) |
Difference
(between current and revised amount) |
Revised Budget (total should equal the original budget) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
|
|
|
EXAMPLE
Budget Modification Template Line Item
|
Original Budget (use budget in grant agreement or prior budget modification) |
Difference
(between current and revised amount) |
Revised Budget (total should equal the original budget) |
Personnel and Consultant Fees |
$53,062.12 |
$50,720.00 |
(2,342.12) |
Consultants Fees |
4,202.72 |
6,600.00 |
2,397.23 |
Travel and per Diem |
1,869.68 |
2,086.00 |
216.32 |
Supplies and Materials |
475.48 |
204.00 |
(271.48) |
Indirect Costs |
15,000.00 |
15,000.00 |
- |
Total |
$74,610.00 |
$74,610.00 |
|
COMPETITIVE NEGOTIATIONS FORM
Any grant that includes professional consultants in the budget must provide the Competitive Negotiations Form along with a resume or CV (2 pages max.) of the selected consultants to National Park Service before requesting an advance or reimbursement. This process ensures that the grantees meet the requirements established for a competitive selection process.
Competitive Negotiations Form (PDF)
CONTACT INFORMATION
National NAGPRA Program
National Park Service
1201 "Eye" Street, NW (2256)
Washington, DC 20005
Attention: NAGPRA Grants
Telephone: (202) 354-1479
Nagpra_grants@nps.gov
Fax 202-371-5197
Or for financial documents to Vedet Coleman, Grants Management Specialist: Fax: 202-371-1794
|
|